Project Overview

Supply and install of two Bryan 8,000,000 BTU steam boilers located at the top of the 24th floor.
Project was completed on schedule and within budget.
The Marriott saved 33% on their gas consumption in the first year with an ROI of 18 months.

Testimonials

"It is without hesitation that we would highly recommend Caon Services for service, new construction, controls and retrofit work"- Barry Graham (DC Sales)

"I do not hesitate to recommend CAON as a source of mechanical services"- Gerry Williscroft (Allied Engineering)

"Caon has received product and service training on the RBI boiler product line, at their facility, and are qualified to service and troubleshoot RBI equipment."- Michael Andersen (Air Chek Industries)

"We have found Caon to be a very capable, both conscientious and reliable, contractor partner to do business with"- Bruce Eastcott (Carrier Canada)

"Caon Services Inc. in Calgary is one of our designated Lochinvar Service providers for the Southern Alberta marketplace."- Darryl Singleton (AquaTech)